How Karpowership Made a Guyana Riverbank Ready for Power
Sixteen Days From Mooring to Full Power
On May 1, 2024, a Karpowership vessel arrived in Georgetown, Guyana. Three days later it sailed up the Berbice River to a jetty at Everton, on the river's east bank. On May 20, sixteen days after mooring there and with the connection work complete, it was delivering its full 36 megawatts to the Demerara-Berbice Interconnected System.
A Riverbank, Not a Port
Everton is not a purpose-built port. No deepwater terminal and no dredged approach channel existed there before the vessel arrived. Guyana Power and Light chose the site for its place on the grid: capacity connected on the Berbice side strengthens that stretch of the interconnected system. The site had to work as it was, and it did.
What Deepwater Access Costs, By Comparison
Elsewhere in the country, Guyana has been paying to dredge roughly nine kilometres of channel, at a cost of 11.2 million US dollars, to give larger vessels access to a different site. That figure is a useful yardstick. It is what building deepwater access for a generation asset can cost, in money and in time, when the ground itself has to be reshaped first. Everton needed none of it. A shallow-draft powership, built to operate from a modest berth rather than a dredged terminal, turned an ordinary riverbank into a generation site within weeks.
Two Vessels, 96 Megawatts
The Everton unit now works alongside a second Karpowership vessel moored at Meadow Bank on the Demerara River, delivering 60 megawatts, for a combined 96 megawatts feeding Guyana's national grid. In July 2026, the two sides agreed a new two-year contract for the Berbice vessel, with Guyana's Public Utilities Minister Deodat Indar explaining the choice of location in the plainest possible terms: "there's a reason why we put the 36 megawatts in Berbice. We put it there so that you can bring up the voltage level on that side."
Site Preparation as the Real Advantage
Guyana is still dredging channels to build the deepwater access its longer-term energy plans will need. What Everton showed is that the slowest part of bringing power to a new place, preparing the site, can be done in weeks when the plant arrives ready to run and the berth only has to be adapted, not built. Any riverbank with the right grid connection is, in principle, a site. As Guyana works toward its Wales gas-to-energy project and the deeper water access that future growth will require, that is a kind of site the country now knows it can bring into service in weeks, not years.
Sources
- Power ship now supplying 36 MW to national grid (opens in a new tab) - Department of Public Information (DPI), 20 May 2024
- Power ship arrives at Everton; connection to begin on Sunday (opens in a new tab) - News Room Guyana, 4 May 2024
- Powership to begin connection to the grid today (opens in a new tab) - Kaieteur News, 5 May 2024
- Guyana's blackout woes nearing an end: GPL powership to be fully integrated into grid today - VP (opens in a new tab) - Guyana Standard, 9 May 2024
- US$1M mobilisation fee for rental of power ship - GPL (opens in a new tab) - INews Guyana, 18 April 2024
- Preparatory work to accommodate power ship at Everton behind schedule (opens in a new tab) - Guyana Times, 1 May 2024
- Powership: GPL considers new substation at Everton to work around any potential failure (opens in a new tab) - News Room Guyana, 22 April 2024
- Guyana to hire Turkish barge to ease blackouts (opens in a new tab) - Demerara Waves, 11 April 2024
- Dredging of Demerara River begins in June (opens in a new tab) - Demerara Waves, 12 May 2026
- Guyana, Karpowership agree to new two-year contract for Berbice vessel (opens in a new tab) - Demerara Waves, 1 July 2026
- Review of powership contracts will be based on progress of gas-to-energy project - Minister Indar says (opens in a new tab) - Guyana Chronicle, 18 August 2026
- Berbice powership deal extended two years at higher rate (opens in a new tab) - HGPTV, 18 August 2026
- Power supply to be boosted as work begins on new cable crossing (opens in a new tab) - Guyana Chronicle, 29 August 2026
- President Ali outlines bold vision of transformation and service as 25 Ministers take Oath (opens in a new tab) - Office of the President, 14 September 2025