Bechtel Takes Over Polish Nuclear Plant Site as Earthworks Begin
Polskie Elektrownie Jądrowe (PEJ) has handed site management for Poland's first nuclear power plant to general contractor Bechtel, with earthworks starting on the construction site, according to World Nuclear News.
The handover coincides with the appointment of Budimex SA, described by World Nuclear News as one of the largest construction companies in Poland, as main contractor for the earthworks at the Lubiatowo-Kopalino site.
That first phase covers ground levelling, reconstruction and expansion of drainage systems, and a temporary road network of about 16 kilometres, per World Nuclear News. Ground movement and levelling will cover a future construction site of more than 300 hectares.
Under the permit obtained, site preparation is scheduled to run from the third quarter of 2026 to the first quarter of 2029. PEJ said it expects to pour first concrete for the plant's first unit in the fourth quarter of 2028, overlapping with the tail end of the preparation window.
More than 200 people are already working at the site, a number PEJ said will steadily increase in the coming months.
The reactor choice dates back to November 2022, when the then Polish government selected Westinghouse AP1000 technology for the Lubiatowo-Kopalino site in the Choczewo municipality in Pomerania, northern Poland.
Source: world-nuclear-news.org (opens in a new tab)1 sourcePermalink