Generation

No U.S. Greenfield Nuclear Project Has Reached Final Investment Decision Despite 10-Reactor Target

No greenfield large-scale U.S. nuclear project has reached a Final Investment Decision (FID), according to Neutron Bytes, even as executive orders target 10 new large reactors under construction by 2030.

A USD 17.5 billion conditional commitment for long-lead equipment was issued in June 2026, covering as many as 10 AP1000 units across five two-unit sites, Neutron Bytes reported. The commitment required USD 500 million upfront each from Westinghouse and utility partners.

The DOE financing office's Section 1706 authority expires on September 30, 2028, setting a hard deadline for converting conditional commitments into binding deals.

Ed Ho said Washington has done "very nearly everything the industry asked of it," according to Neutron Bytes. "The last mile now belongs to the people with the balance sheets," Ho said.

Source: neutronbytes.com (opens in a new tab)1 sourcePermalink