  • AI Data Center Demand Strains Gas Turbine Supply, Pushing Wait Times to Six Years.
  • COP31 Talks Stall in Türkiye as Fossil Fuel Language Divides Delegates.
  • Early polar vortex disruption and El Niño strain Europe's depleted gas reserves.
  • Federal Orders Keeping Six Coal Plants Running Have Cost Ratepayers About USD 593 Million.

AI & Energy

AI Data Center Demand Strains Gas Turbine Supply, Pushing Wait Times to Six Years

AI data centers are driving a surge in gas turbine orders, according to the Chosun, stretching delivery timelines and forcing buyers to seek unconventional alternatives.

In the U.S., receiving a newly ordered gas turbine now takes an average of six years, Reuters reported, as cited by the Chosun. The bottleneck has prompted efforts to source used turbines or repurposed jet engines as stopgap power solutions for data center construction.

Crusoe, a U.S. AI infrastructure company, ordered 13 gas turbines converted from GE Aerospace jet engines, totaling 650 MW of capacity, for its AI data center projects in the U.S., the Chosun reported.

Source: chosun.com (opens in a new tab)1 sourcePermalink