Urenco to Add 2.1 Million SWU at New Mexico Enrichment Plant
Urenco will invest a multi-billion-dollar sum to increase enrichment capacity by nearly 50% at Urenco USA's National Enrichment Facility, with construction starting in 2029 and first low-enriched uranium production in 2032.
The expansion adds 2.1 million separative work units (SWU) at the Eunice, New Mexico site, currently the only commercial uranium enrichment capacity in the United States.
Boris Schucht, CEO of Urenco Global, said the project "reinforces our commitment to a resilient US nuclear fuel supply chain" and supports US energy security through continued investment.
The new plant will run gas-centrifuge technology in up to 24 cascades, with the first cascades producing low-enriched uranium in 2032 and additional cascades coming online through 2036.
The Eunice site already runs about 64 cascades producing roughly 4.3 million SWU per year, enough to meet nearly one-third of annual US enrichment demand. A separate ongoing expansion to add 700,000 SWU is due for completion in 2027.
The project will support 300 to 600 US jobs during peak construction and 70 long-term operations jobs at the site.
The US work forms part of a Urenco Global program to install 4.6 million SWU of new enrichment capacity across the United States, the Netherlands, and Germany over the next decade.
Source: world-nuclear-news.org (opens in a new tab)1 sourcePermalink