UK Grid Reform Flags Battery Surplus, Opens Industry Consultation
Too many battery storage projects have cleared a key stage of the reformed grid connection queue, and UK officials are now asking industry whether to intervene. Energy Minister Michael Shanks and Ofgem infrastructure chief Akshay Kaul set out the concern in an open letter dated April 16, 2026.
DESNZ and Ofgem issued the joint update on connections reform delivery and on how much battery capacity sits in the reformed queue.
Shanks and Kaul flag a high volume of battery storage projects moving through to Gate 2, more than the capacity ranges laid out in the Clean Power 2030 Action Plan.
The two officials ask whether further measures should be taken to address that surplus, and point industry to the National Energy System Operator's (NESO) annual consultation on its connections methodologies as the channel for responses.
Gate 2, the point where projects lock in firm connection terms, is where the excess has surfaced against the plan's targets. Views submitted through the NESO process will shape whether the queue rules are adjusted.
Source: gov.uk (opens in a new tab)1 sourcePermalink