Key points

  • DOE Names Utah, Tennessee, Oklahoma, Louisiana and Idaho as Nuclear Campus Contenders.
  • Keppel Sets Up USD 2.86 Billion Fund to Sell Down 10 Legacy Drilling Rigs.
  • PosHYdon Pilot Produces First Offshore Green Hydrogen on Q13a-A Platform.
  • Taiwan's New Solar Rules for Large Buildings Seen Adding 660 MW a Year.

Grid & Storage

Puerto Rico Energy Bureau Clears 100 MW/400 MWh Battery at Former Yabucoa Refinery Site

The Puerto Rico Energy Bureau conditionally approved a 100 MW/400 MWh battery energy storage project proposed by Yabucoa Energy LLC, according to ESS News, clearing the contract subject to several modifications.

The four-hour system sits in the municipality of Yabucoa, in the island's southeast, on the site of the former Shell refinery, ESS News reported.

Yabucoa Energy will develop, operate and maintain the battery under a 20-year energy storage services agreement with the Puerto Rico Electric Power Authority (PREPA), according to ESS News.

The regulator attached a durability condition to that term. Yabucoa Energy must hold the full 400 MWh discharge capacity across the whole 20 years, replacing or expanding system components as necessary, ESS News reported. That obligation shifts battery degradation risk onto the developer rather than the offtaker for the life of the contract.

On the cost side, the agreement assumes interconnection infrastructure costs of up to USD 20 million, ESS News reported. If the final figure comes in below that ceiling, contract payments must be cut by the difference.

Source: ess-news.com (opens in a new tab)1 sourcePermalink

Grid & Storage

Moranbah Solar-Plus-Storage Clears AEMO Connection Approval in Bowen Basin

The Moranbah Solar Farm and battery project has cleared 5.3.4A Connection Approval with the Australian Energy Market Operator (AEMO), clearing the grid hurdle for Grupo Cobra and its developer subsidiary Zero-E Australia, ESS News reported.

Rated capacity at the site is 145 MW of solar generation, sitting alongside a battery energy storage system of 50 MW and 100 MWh.

The hybrid plant is sited in the Bowen Basin, which ESS News identifies as Australia's largest coal-producing region.

Zero-E has put construction start at mid-2027, with first operation tipped for early 2029.

Output will reach the network at Ergon Energy's 132 kV Broadlea substation, according to ESS News.

Moranbah holds a contract from Tender 7 of the Capacity Investment Scheme, one of 19 projects picked in that round. Tender 7 underwrites 7.8 GW of renewable generation and 7.9 GWh of storage through long-term revenue guarantees, ESS News reported.

Up to 250 jobs are expected during the build phase.

Source: ess-news.com (opens in a new tab)1 sourcePermalink

Grid & Storage

Neoen Starts Work on Second Italian Battery Project, Flags Grid and Permitting Limits

Neoen has begun construction on its second battery energy storage project in Italy, according to ESS News. The developer told the outlet that the next phase of storage deployment in the country will hinge less on technology and financing availability than on grid infrastructure, permitting and regulatory certainty.

The new site is the Pasian di Prato Battery in Friuli-Venezia Giulia, a 25 MW/100 MWh system, as reported by ESS News. The four-hour asset secured a capacity market contract in February 2025 and is expected to enter operations in 2027.

Neoen's first Italian battery, the 10 MW/40 MWh Broni Battery, remains under construction, ESS News reported.

On the generation side, the company's 7.4 MWp Arena Po solar plant in Pavia province started feeding electricity into the grid in early 2026 and is now fully operational, according to ESS News. Output is expected to reach 11.9 GWh a year, sold under a 10-year power purchase agreement signed with data center operator Equinix.

Across its portfolio, Neoen said it holds 120 MW of solar capacity and 2.3 GW of combined battery storage and solar capacity globally.

Source: ess-news.com (opens in a new tab)1 sourcePermalink

Grid & Storage

Georgia Power Brings 49.5 MW Moody Battery Site Online

Georgia Power has commissioned the Moody Battery Facility, one of the utility's first battery energy storage system sites tied to solar generation, according to Solar Builder.

The installation sits just outside Valdosta in southern Georgia and holds 49.5 MW of capacity, Solar Builder reported. That capacity can be discharged to the state grid over a period of about four hours.

Moody was cleared alongside three other battery projects in the state, a group Solar Builder puts at 715 MW combined, under the 2023 update to Georgia's Integrated Resource Plan.

Approval reaches well beyond that first tranche. The Georgia Public Service Commission has signed off on construction of nine further battery energy storage facilities, which Solar Builder said plan to add more than 3 GW of storage to the Georgia grid once online.

The utility also secured approval for two new solar systems with adjacent storage in Laurens and Dougherty counties, a combined 350 MW, per Solar Builder.

Source: solarbuildermag.com (opens in a new tab)1 sourcePermalink

Grid & Storage

Spain's State Bulletin Lists 260 MW of Battery Storage in Permitting Round

Spain's official state bulletin (BOE) published details of seven renewable energy projects approved or submitted for permitting during the third week of July, covering 260 MW of battery energy storage systems, according to ESS News.

The filings also cover 40.5 MW of renewable hybridization projects, ESS News reported.

The largest single approval went to Bruc Energy, which secured administrative approvals for four battery storage modules to be developed in Alcalá de Guadaíra, Seville, according to ESS News. Each module carries a capacity of 39.6 MW.

FRV requested authorization for a BESS project in Camargo, Cantabria, rated at 49.94 MW, per the same report.

A smaller application came from Dargon Energy, which submitted plans for a storage facility of 4.99 MW in L'Arboç, Tarragona, ESS News said.

Solaria filed for a 45 MW battery storage module to be hybridized with its Agrupación Maira Gamma solar project in Briviesca, Burgos, according to ESS News. The solar plant is rated at 140.127 MW.

Source: ess-news.com (opens in a new tab)1 sourcePermalink