ERCOT Delays First Data Center Connection Batch to Mid-December for Governor's Audit
The first group of large data centers queued for connection to the Texas grid will not advance until mid-December, ERCOT officials said, according to Inside Climate News.
The holdup covers Batch Zero, a set of 300 projects that ERCOT staff must vet. Inside Climate News reported that 90 percent of those projects are data centers.
Batch Zero was set up to refine how ERCOT studies the 1,800 projects waiting for grid connection, according to the same report.
Chad Seely, ERCOT's senior vice president for regulatory policy, said the grid operator is now running the audit and verification earlier in the study process at the request of the governor. Seely made the remarks at a PUC meeting, per Inside Climate News.
Water use data on the sector remains thin. A PUC water survey released in April has drawn responses from only 28 companies, Inside Climate News reported.
Public sentiment in the state runs against local siting. A June poll from the University of Texas at Austin and the Texas Politics Project found 56 percent of respondents opposed building data centers in their communities, with 42 percent strongly opposed.