Nova Scotia brings three 50 MW battery storage sites online
Three grid-scale battery storage facilities in Nova Scotia, each rated at 50 MW and 200 MWh with four-hour duration, are now operational, according to SaltWire. One of the sites is in White Rock, with the other two located in Bridgewater and Waverley.
The White Rock facility began operating on Sept. 3 after performance testing and commissioning in August, McLellan told SaltWire.
McLellan said the sites are transmission connected, and their main purpose is to draw renewable energy from the transmission grid and feed it back as needed. He added that the batteries could also serve as a backup in the event of a power outage.
Source: saltwire.com (opens in a new tab)1 sourcePermalink